What needs a permit in Wanneroo
| Project | Building permit? | Planning approval? |
|---|---|---|
| Shed | Not for one shed under 10 m² and under 2.4 m high; yes for anything bigger | Usually not, if it meets the R-Codes |
| Patio | Not if freestanding, 10 m² or less and 2.4 m or less; every attached patio needs one | Usually not, if it meets the R-Codes |
| Carport | Always | Only for R-Code variations |
| Deck | Always, whatever its height or size | May be needed above 500 mm from natural ground |
| Granny flat | Always | May be needed |
When planning approval is needed, the City says it must be granted before the building permit.
What to lodge
For an uncertified (BA2) application, Wanneroo's information sheets ask for:
- A site plan at 1:200 or larger, with levels, setbacks, any septic system and a north point
- Floor plan, elevations and sections at 1:100
- Structural engineer's details, where the structure needs them
- A Street and Verge Bond application, if it applies
Wanneroo has separate BA1 and BA2 checklists for houses and granny flats, and a separate checklist for unauthorised work.
Fees
Building permit fees are set by the state: 0.32% of the value for a BA2, or 0.19% for a BA1, at least $121, plus the Building Services Levy ($61.65 up to $45,000). Wanneroo also charges a $140 verge bond fee and a $2,200 bond for work of $20,000 or more.
How long it takes
A complete BA1 must be decided within 10 business days and a BA2 within 25 business days. Planning approval usually takes up to 60 days, or 90 with consultation. Use the approval timeline calculator to work out yours.
Compare with City of Stirling building permits or City of Swan building permits.