How long will my approval take?
Up to three quick questions.
The time limits at a glance
| Approval | Time limit |
|---|---|
| Building permit, BA1 (certified) | 10 business days |
| Building permit, BA2 (uncertified) | 25 business days |
| Supplying more information if asked | Usually 21 days |
| Planning approval, no consultation | 60 days |
| Planning approval, with consultation | 90 days |
These limits come from the state rules, so they're the same across WA. Councils such as Swan, Melville and Stirling publish them.
When the clock starts
The clock only starts once the council has a complete application. The City of Swan says it starts at midnight the day after a complete application is received. A missing form, plan or fee can add weeks before anything happens.
What slows things down
- Missing documents. The council asks for more information, and the clock pauses.
- Not replying in time. If you miss the 21 days, the City of Swan says it may refuse the application, and fees are unlikely to be refunded.
- Planning approval. It must come first, and it's the longest step.
- Surveyor turnaround. For a BA1, the private surveyor's time comes before the 10 days.
Not sure which form to use? Read BA1 vs BA2, or planning approval vs building permit.