Council guide

City of Canning building permits

Short answer

In the City of Canning, most building work needs a building permit. Small freestanding sheds (10 m² or less, 2.4 m or lower), pergolas up to 20 m² and some repairs are exempt. The City decides in 10 working days (BA1) or 25 (BA2). Planning approval is usually only needed if you don't meet the R-Codes.

Last updated 24 November 2026

Work that doesn't need a building permit

The City of Canning follows the state's list of exempt work. The main ones for homes:

WorkNo permit if
Freestanding shed, garage or carport10 m² or less and 2.4 m high or less
Pergola (open roof)20 m² or less and 2.4 m high or less
Fence or screenBuilt to the City's local laws, or masonry up to 0.75 m, other materials up to 1.8 m. Pool fences always need a permit
Retaining wallHolds back 0.5 m of soil or less, isn't part of other building work and doesn't affect next door
Water tank5,000 litres or less
Solar panels or solar hot waterOn the roof of a house or a shed that goes with it
Repairs and renovationsNot structural, similar materials, no change to size or height, not heritage listed

Exempt work must still meet the building rules and any planning rules.

Planning approval

For a house on its own lot, planning approval is usually only needed if it:

  • doesn't meet the R-Codes deemed-to-comply rules,
  • is in the aircraft noise special control area, or
  • is in a bushfire prone area.

Compliant patios, sheds, carports and garages on non-heritage lots don't need planning approval. Two or more homes on a lot (grouped dwellings), apartments, and work on commercial or industrial land always need it. The City offers a deemed-to-comply check if you're not sure.

Applying for the permit

  • BA1 (certified): needs a Certificate of Design Compliance from a private building surveyor. The City decides within 10 working days.
  • BA2 (uncertified): the City checks the plans itself, for houses and Class 10 buildings only. It decides within 25 working days.

If the City asks for more information, you have 21 days to send it. You can lodge online. Building Services is on 1300 422 664, weekdays 8.15am to 5pm, and also has info sheets on patios, sheds, carports, granny flats, pools and retrospective approval.

See what doesn't need a permit, which BA form to use and retrospective approval.

Sources

Questions

Common questions

What doesn't need a building permit in the City of Canning?

Small freestanding sheds and carports (10 m² or less, 2.4 m or lower), pergolas up to 20 m², water tanks up to 5,000 litres, rooftop solar on a house, low retaining walls and many repairs.

Do I need planning approval for a house in Canning?

Usually not, unless it breaks the R-Codes deemed-to-comply rules or is in the aircraft noise or bushfire prone areas.

How long does the City of Canning take to issue a building permit?

10 working days for a certified (BA1) application and 25 working days for an uncertified (BA2) one.

How do I contact City of Canning Building Services?

Call 1300 422 664 between 8.15am and 5pm on weekdays, or send an online enquiry.

Hand over the paperwork.

Pick your project, tell us about it, and we take it from there: plans, forms, council, and updates until your permit is issued.

P.S. Not sure you even need a permit? Ask anyway. If you don't, we'll tell you, and it costs nothing.

Get my priceCall