BA1 or BA2?
| BA1 (certified) | BA2 (uncertified) | |
|---|---|---|
| Who checks the plans | A private building surveyor, who signs a Certificate of Design Compliance (BA3) first | The City's building surveyors, who issue the BA3 with the permit |
| What you lodge | BA1, BA3 and the drawings listed on the BA3 | BA2, site plan, floor plans, elevations, sections, construction details and engineering |
| City's decision time | 10 business days | 25 business days |
All commercial building permits in Rockingham must be certified (BA1).
What needs a permit
The City lists fences, pools, spas and barriers, garden sheds, verandahs, gazebos, garages, workshops, pergolas, houses, retaining walls and changes to ground levels (cut and fill). Some small work is exempt under the state Building Regulations 2012, such as a freestanding shed of 10 m² or less and 2.4 m or less high.
If the work is worth more than $20,000, the permit is issued to a registered builder or an approved owner-builder. Since 1 July 2026, the limit for a shed, garage or carport is $50,000.
What goes in a BA2
- A site plan at 1:200 or larger, with spot levels, all existing buildings, boundary setbacks, any septic system and a north point.
- Floor plans, elevations and sections at 1:100, with all dimensions.
- Construction details showing all materials and sizes.
- Structural details designed and certified by a practising structural engineer.
Fees are paid when you lodge. You can lodge online through the City's Rock Port portal, in person at the Civic Boulevard office, or by post.
Planning approval first?
Most houses and home projects on residential lots only need a building permit if they meet the R-Codes. But any development on Special Residential or Special Rural land needs Town Planning consent first, including changes to a building envelope. Commercial, industrial and three or more grouped dwellings also need a development application.
Time limits and after you build
- A permit usually lasts 2 years. Rockingham's page says it's void if work hasn't started within 12 months.
- The builder must lodge a BA7 notice of completion within 7 days of finishing.
- Copies of old building plans cost $60 for a residential set or $25 per plan, and can take up to 10 working days.
Already built without a permit?
Building without a permit can bring a penalty of up to $50,000 for a first offence. To fix it, you lodge a BA13 building approval certificate application with a BA18 certificate of building compliance from a registered building surveyor. On rural and special zones you need retrospective planning approval first.
See which BA form you need, how to check if a building is approved, or retrospective approval. Call the City on 9528 0333.