Question answer

What is a BA7 notice of completion?

Short answer

The BA7 is the form the builder named on your permit lodges with the council when the work is finished. It must go in within 7 days of completion, with certificates for any inspections or tests the permit listed. Not lodging it can bring a penalty of up to $10,000.

Last updated 11 November 2026

What the BA7 is for

A building permit doesn't end when the last screw goes in. Under section 33 of the Building Act, the builder named on the permit must tell the council the work is finished. That notice is form BA7, Notice of completion. It closes off the permit on the council's records.

The key rules

RuleDetail
Who lodges itThe builder or demolition contractor named on the permit. If you're the owner-builder, or you built a small Class 10 job yourself, that's you.
WhenWithin 7 days of finishing the work, or the stage of work the permit covered
WhereThe permit authority, usually your council
FeeNone listed on the form
Penalty for not lodgingUp to $10,000

What goes on the form

The current BA7 (approved 17 July 2026) is two pages:

  1. Property: the address or lot number, and the permit number
  2. Details: whether it's building or demolition work (or a stage), the date of completion, the final value of the contract, and whether it includes a pool, spa or pool barrier
  3. Builder: name, registration, licence or owner-builder approval number, and contact details
  4. Notification: you sign to say you're the builder on the permit, the work is finished, and you've attached a certificate for each inspection or test listed on the permit
  5. Inspections and tests: dates and types, with the certificates attached

Common questions councils get

  • What inspections? Only those listed on your permit. New pools also have their safety barrier inspected by the council.
  • Does it let me move in? Houses, granny flats and outbuildings (Class 1 and 10) don't need an occupancy permit. For Class 2 to 9 buildings, the form says the BA7 doesn't authorise occupancy.
  • The builder changed halfway? That's a different form: the BA8, Notice of cessation.

Some councils, such as Gosnells, remind owners that the BA7 is still needed even when other steps are done. Councils vary in how they accept it, so check your council's website.

Not sure which form you need at the start? See which BA form do I need?, the permit jargon guide, or how to fill in a BA2.

Sources

Questions

Common questions

What is a BA7 in WA?

A BA7 is the Notice of completion. The builder named on the building or demolition permit lodges it with the council to say the work is finished.

How long do I have to lodge a BA7?

Within 7 days of finishing the work, or the stage of work, that the permit covered.

What happens if I don't lodge a BA7?

Not lodging it can bring a penalty of up to $10,000.

Who signs the BA7?

The builder or demolition contractor named on the permit. For owner-builders, that's the owner.

Does a BA7 let me occupy a building?

It doesn't authorise occupancy of a Class 2 to 9 building that needs an occupancy permit. Houses and outbuildings don't need one.

Hand over the paperwork.

Pick your project, tell us about it, and we take it from there: plans, forms, council, and updates until your permit is issued.

P.S. Not sure you even need a permit? Ask anyway. If you don't, we'll tell you, and it costs nothing.

Get my priceCall